Tanga PPP Projects: 17 Sites, Their Status and How an Investor Engages Now

What are the Tanga PPP projects and can investors bid now? Tanga Region shortlisted 17 council projects for public-private partnership at a forum on 12 November 2026: bus stands, a dry port, markets, an abattoir, hotels, a cassava mill and a quarry. All hold title deeds, but feasibility studies are still pending. Investors can register interest and prepare proposals now; no tender has opened.
The Tanga PPP projects are a regional list of council-owned schemes now open to private investors. At the Tanga PPP Economic Forum on 12 November 2026, the Public Private Partnership Centre (PPPC) and the Tanzania National Chamber of Commerce (TNCC) presented 17 projects owned by Tanga's councils. They span transport, trade, tourism, livestock, agriculture and quarrying. This post sets out what was announced, where each project stands, and the legal route an investor uses to engage.
It does not repeat the national framework. Our public private partnership guide covers the Act, approvals and bid stages in full. Here we focus on the Tanga list and what to do this month.
What changed
Three reports confirm the forum and the list. TanzaniaInvest reported on 13 November 2026 that 19 projects were identified and 17 shortlisted after screening. The Respondent previewed the forum on 11 November, and Streamline Feed reported on 13 November that studies were still pending.
The speakers were PPPC Executive Director David Kafulila, TNCC Executive Director Oscar Kisanga and Tanga Regional Commissioner Dr Batilda Burian. The main points reported were these:
- All 17 shortlisted projects hold title deeds. Two quarry proposals, Bumbuli Stone Quarry and Mivyasa Mining Extraction, were dropped for lacking them.
- The mix is 10 greenfield, 6 brownfield and 1 yellowfield project. The reports do not say which project is which.
- The Regional Commissioner directed district commissioners and council directors to prepare full feasibility studies and project documents for the local proposals.
- The PPPC said it will fund a dedicated PPP strategy for Tanga Region.
- Kafulila and Kisanga explained that projects below USD 20 million no longer need national approval at the top tier, and that the government can co-finance capital costs through viability gap funding.
A follow-up analysis on 26 November 2026 adds that the regional secretariat must report progress on the forum resolutions every three months. It also confirms that no final investment agreement has been reached on any project.
One discrepancy matters for anyone pricing a bid. The Respondent's preview lists quarries at Handeni, Bumbuli and Kilindi. The post-forum list carries one quarry, at Handeni, and records Bumbuli as dropped. We follow the post-forum list below and treat the final list as something to confirm with the council.
Who is affected
- Developers and operators of bus terminals, lorry parks and logistics yards.
- Hotel groups and property developers looking at Tanga City and the Pangani coast.
- Agro-processors, abattoir operators and cross-border traders using the Horohoro border with Kenya.
- Quarry operators and construction-material suppliers.
- Foreign investors who would need an SPV, TISEZA registration and a land route before any agreement is signed.
- Tanzanian firms that want to partner with a foreign sponsor or bid alone on the smaller sites.
Which 17 projects are on the Tanga list?
The table follows the TanzaniaInvest list of 13 November 2026. Sectors for the last five rows are our reading of the project type. Areas are as reported.
| # | Project | Location | Sector | Area (m²) |
|---|---|---|---|---|
| 1 | Pongwe Dry Port | Tanga City | Transport | 595,785 |
| 2 | Horohoro parking lots | Mkinga | Transport | 20,234 |
| 3 | Mombo Bus Stand | Korogwe | Transport | 19,236 |
| 4 | Mkata Lorry Park | Handeni | Transport | 24,281 |
| 5 | Muheza Main Bus Stand | Muheza | Transport | 14,000 |
| 6 | Pangani Bus Stand | Pangani | Transport | 12,276 |
| 7 | Dr Samia Suluhu Business Centre | Tanga City | Trade | 40,000 |
| 8 | Horohoro Border Crop Market | Mkinga, Kenya border | Trade | 121,406 |
| 9 | Korogwe Commercial Centre | Korogwe | Trade | 3,600 |
| 10 | Business and sports project | Pangani | Trade | 2,970 |
| 11 | Modern fish market | Pangani | Trade | Not stated |
| 12 | Lushoto Business Centre | Lushoto | Trade | 1,069 |
| 13 | Tanga City Abattoir | Tanga City | Livestock | 74,400 |
| 14 | Tanga City Hotel | Tanga City | Tourism | 17,800 |
| 15 | Beach hotel | Pangani | Tourism | Not stated |
| 16 | Cassava processing mill | Mkata, Handeni | Agriculture | Not stated |
| 17 | Building stone quarry | Handeni | Mining | 174,014 |
Two other Tanga schemes sit outside the list. The Tanga to Handeni to Singida road PPP is in investor screening and due diligence. The dry port roadmap with the Tanzania Ports Authority is also separate from Pongwe.
What stage are the projects at?
Early. A title deed means the council can offer the land. It does not mean the project is ready to procure. Under the Public Private Partnership Act, Cap. 103 R.E. 2023, every contracting authority must undertake or cause to be undertaken a feasibility study (section 13(1)). That study is what the PPPC and the Steering Committee review before procurement.
For the Tanga list, the reports agree on four points:
- No feasibility study is reported complete for any of the 17.
- None of the reports mentions a call for expressions of interest or a request for proposals for them.
- No financing is secured, and no agreement is signed.
- The PPPC news page had no Tanga notice when we checked on 28 November 2026.
That makes this a pipeline, not a tender. The useful work now is preparation, not bidding.
What the law says
The Mainland framework rests on four instruments.
- Public Private Partnership Act, Cap. 103 R.E. 2023. The Revised Edition published by the PPPC folds in the amendments of 2014, 2018 and 2023. Section 2(1) applies it to Mainland Tanzania. Section 3 lists a local government authority as a contracting authority.
- Public Private Partnership (Amendment) Act, No. 4 of 2023. Passed on 13 June 2023, assented on 5 July and gazetted on 14 July 2023, as FB Attorneys reported on 24 July 2023. It required an SPV before signing and opened arbitration under ICSID rules or investment treaties. It also restored tax incentives under investment law and made the PPP Act prevail over conflicting laws.
- Public Private Partnership Regulations, 2020, GN 37 of 2020. Published on 24 January 2020, they set the procedure. The Ministry of Finance copy sets out the PPP Node for local government projects and the unsolicited route.
- Public Private Partnership (Amendment) Regulations, 2023, GN 838A of 2023. Clyde and Co summarised them on 10 June 2024: the commitment deposit was removed and the review fee capped. Prefeasibility tests were also tightened.
A note on numbering. The R.E. 2023 text renumbered the sections. Competitive bidding is now section 21 (formerly 15), unsolicited proposals section 22 (formerly 16), and the SPV section 25. Disputes are section 29 and precedence over other laws is section 38. Older guides and some official slides still use the 2019 numbers.
How does an investor engage with a council PPP?
Every Tanga project has a council as its contracting authority. That shapes the route. Regulation 3(4) of GN 37 of 2020 sends a council's potential projects to the PPP Node in the ministry responsible for local government. The Node scrutinises them and forwards selected projects to the PPPC.
The Node also reviews councils' prefeasibility studies and evaluation reports before they reach the PPPC. Communications on an unsolicited proposal go through the contracting authority, not straight to the PPPC (regulation 10(3)).
In practice, the first conversation for a Tanga site is with the council director who owns it. The PPPC is the second. The PPP Centre sits at Government City, Mtumba, Dodoma, and publishes its project list, expressions of interest and standard documents.
Solicited or unsolicited: which route fits a Tanga site?
Section 21(1) requires open and competitive bidding as the default. An investor can wait for the council to procure, or bring its own proposal.
| Point | Solicited (council-led) | Unsolicited (investor-led) |
|---|---|---|
| Who studies feasibility | Council, reviewed by the Node and PPPC | The private party, at its own cost (s.22(1)) |
| Where it starts | Council prefeasibility study | Prefeasibility study lodged with the council (reg. 7(1)) |
| Competition | Open bidding (s.21(1)) | Open bidding unless the Minister exempts it (s.21(2)) |
| Government support | Viability gap funding possible | An exemption needs no guarantee or financial support |
| Review fee | None reported | Review fee under reg. 9(1); confirm with the PPP Centre |
| Best fit in Tanga | Bus stands, markets, lorry parks | Dry port, abattoir, hotel, cassava mill |
The section 21(2) exemption has seven tests. They include priority to government, no guarantee or financial support, and unique attributes. Significant size, value for money, wide socio-economic benefits and the proponent bearing the study cost complete the list. Most small Tanga sites will not meet the size test. Expect them to go to open bidding.
Do projects under USD 20 million follow a lighter route?
Yes, in part. Section 3 of Cap. 103 R.E. 2023 defines a small-scale PPP project as one not exceeding twenty million US dollars. Section 10(3) lets the Minister issue directives to accounting officers on those projects. Under regulation 16(2), the PPPC rather than the Steering Committee makes the recommendation to the contracting authority for small-scale projects.
Most of the Tanga list will fall in this band. The exception is likely the Pongwe Dry Port, given its 59.6 hectares. The approval path is shorter, but the feasibility study, PPPC review and Attorney General vetting under section 20 still apply. The accounting officer signs under section 24(1) after the required approvals.
Worked example: a foreign-owned SPV for the Tanga City Hotel
Assume a South African hotel group wins or negotiates the Tanga City Hotel site. It forms a Tanzanian SPV with nominal share capital of TZS 400 million. Its managing director, a South African national, needs permits. It seeks a TISEZA certificate and agrees an annual reserved rent of TZS 120 million with the council. The rent is our assumption; every fee is from the Zatra register.
| Step | Authority | Register line | Amount |
|---|---|---|---|
| Company name reservation | BRELA | F0003 | TZS 50,000 |
| Incorporation, share capital TZS 100m to 500m | BRELA | F0001 | TZS 450,000 |
| Stamp duty, memorandum and articles | TRA | NEW-02-26 | TZS 20,000 |
| Investor registration | TISEZA | TZ-03 | TZS 300,000 |
| Certificate of incentives, foreign investor | TISEZA | TZ-01 | TZS 6,000,000 |
| Stamp duty, lease at 1% of annual rent | TRA | F0265 | TZS 1,200,000 |
| Residence permit Class A via TISEZA | Immigration | F0403 | USD 3,050 plus USD 305 facilitation |
| Work permit Class A, investor | Labour Commissioner | F0413 | USD 1,000 |
| Work permit facilitation via TISEZA | TISEZA | F0418 | USD 100 |
Government fees in this example total TZS 8,020,000 and USD 4,455, kept apart by currency. The TISEZA certificate also needs minimum investment capital of TZS 1,500,000,000 for a foreign-owned business (register TZ-02). If the land comes through a derivative right, TISEZA charges 10% of the Ministry of Lands title charge (register F0473).
Once trading, the hotel pays the council hotel levy of 2% of guest charges (register F0283). Two costs stay open: the PPP review fee, if the route is unsolicited, and the hotel's tourism licence. Confirm both with the PPP Centre and the licensing authority. Zatra's professional fee is quoted separately and never folded into these lines.
How does a foreign investor hold the land?
The councils hold the titles. A foreign-controlled SPV cannot take an ordinary right of occupancy in its own name. Section 19(2) of the Land Act, Cap. 113, as at 30 June 2025 limits non-citizens to three interests. They are a right of occupancy or derivative right for investment approved under the Investment and Special Economic Zones Act, or an interest under a joint venture or partial transfer.
Section 18 of Cap. 103 sends any land acquisition for a PPP through the Land Act and related land laws. The PPP agreement will set the tenure, but the mechanism should be agreed with TISEZA and the council before price is fixed. Our guide to derivative rights and investor leases explains the structure. Run an official title search on the council's deed before any commitment.
Where does TISEZA fit in?
TISEZA replaced TIC and EPZA from 1 July 2025 under the Investment and Special Economic Zones Act, No. 6 of 2025. Section 28 of Cap. 103 gives a qualifying PPP project the benefits of investment law. In practice that means a TISEZA certificate.
A TISEZA presentation of July 2025 places the PPP framework alongside TISEZA's facilitation role. It counted 83 national projects across the stages from concept note to implementation. Our TISEZA certificate guide covers the application. Registration fees are TZS 300,000 (register TZ-03) and the certificate fee TZS 6,000,000 for a foreign investor (register TZ-01).
Can a foreign investor take the quarry or the market sites?
Not always on its own. Two rules need checking before a foreign sponsor bids:
- Quarry. A building stone quarry needs a mining licence under the Mining Act, Cap. 123. A Primary Mining Licence is not available to foreigners (register F0619). A foreign sponsor would need to confirm a licence class open to it, or partner with a Tanzanian holder.
- Markets and commercial centres. GN 487A of 2025 reserves 15 activities for citizens, including most wholesale and retail trade (register NEW-08-14). A foreign operator can develop and manage a building, but its tenants' trades matter.
Section 33 of Cap. 103 also asks projects to provide opportunities for citizen empowerment. Expect councils to score local participation.
How is Zanzibar different?
Tanga is on the Mainland, so Cap. 103 applies. Zanzibar runs its own regime. The Zanzibar PPP Department administers the Public Private Partnership Act, No. 8 of 2015, with a 2014 policy and 2017 regulations. The Department sits in the President's Office for labour, economic affairs and investment.
| Point | Mainland (Tanga) | Zanzibar |
|---|---|---|
| Law | PPP Act, Cap. 103 R.E. 2023 | PPP Act, No. 8 of 2015 |
| Agency | PPP Centre, Dodoma | PPP Department, President's Office |
| Investor registration | TISEZA | ZIPA |
| Company registry | BRELA | BPRA |
| Land for foreigners | Land Act s.19(2), derivative right | Zanzibar land law, via ZIPA |
A Mainland PPP approval does not carry across. Our guide to investing through ZIPA covers the island route.
What to do now
- Shortlist one or two sites. Match the project type to your operating record, and check the 16 or 17 count with the council.
- Contact the council director. Ask for the title deed, the land use plan and any prefeasibility notes for the site.
- Register on the PPP Centre list. Watch its expressions of interest page and ask to join market sounding sessions.
- Choose the route. Decide whether to wait for a solicited tender or fund an unsolicited prefeasibility study.
- Test foreign eligibility. Check GN 487A, mining licence classes and the land route before you spend on studies.
- Prepare the vehicle. Plan the SPV, shareholders and any public stake up to 25% (section 25(2)).
- Line up TISEZA. Confirm the minimum capital and certificate timing so incentives apply from the start.
- Budget two buckets. Keep government fees and advisers' fees separate, with study costs priced as a third line.
Key dates
| Date | Event |
|---|---|
| 24 January 2020 | PPP Regulations, GN 37 of 2020, published |
| 14 July 2023 | PPP (Amendment) Act, No. 4 of 2023, gazetted |
| 1 July 2025 | TISEZA replaces TIC and EPZA |
| 12 November 2026 | Tanga PPP Economic Forum presents 17 projects |
| 13 November 2026 | Project list reported by TanzaniaInvest and Streamline Feed |
| 26 November 2026 | Follow-up confirms no agreement signed and quarterly reporting |
| Every three months | Regional secretariat progress report on forum resolutions |
| Not announced | Feasibility study completion, tender or EOI dates |
How Zatra helps
Our investment advisory team screens Tanga sites against your sector and eligibility. The feasibility studies team builds prefeasibility studies and financial models in the form the PPPC reviews. We form the SPV through our company registration service. Our TISEZA registration desk files the certificate, and the tender advisory team prepares bids when councils procure.
Zatra prepares and coordinates the file but does not decide or guarantee any authority's outcome. Government fees are paid at the official rate against the authority's control number, separate from Zatra's professional fee. Route legal opinions on a PPP agreement, land conveyancing, disputes and arbitration to an advocate. Fee lines are listed in our government fees guide.
Sources and status
Accurate as at 28 November 2026. Section numbers for Cap. 103 were read in the R.E. 2023 text published by the PPP Centre. Regulation numbers were read in GN 37 of 2020. Fees come from the Zatra fee register, stated at 26 September 2026.
- 17 PPP projects open in Tanga to investors. TanzaniaInvest, 13 November 2026. Accessed 28 Nov 2026.
- Tanga turns to private investors (forum preview). The Respondent Online, 11 November 2026. Accessed 28 Nov 2026.
- Tanga opens 17 PPP projects to investors, studies pending. Streamline Feed, 13 November 2026. Accessed 28 Nov 2026.
- Can private capital deliver Tanga's promised economic transformation? The Respondent Online, 26 November 2026. Accessed 28 Nov 2026.
- Public Private Partnership Act, Cap. 103 R.E. 2023. PPP Centre and Office of the Attorney General, 2025 print. Accessed 28 Nov 2026.
- Public Private Partnership Regulations, 2020, GN 37 of 2020. Ministry of Finance, 24 January 2020. Accessed 28 Nov 2026.
- Public Private Partnership Centre. PPP Centre, home and news pages current November 2026. Accessed 28 Nov 2026.
- Public Private Partnership Act amended. FB Attorneys, 24 July 2023. Accessed 28 Nov 2026.
- Tanzania PPP Regulations amendments, 2023. Clyde and Co, 10 June 2024. Accessed 28 Nov 2026.
- Land Act, Cap. 113. TanzLII, text as at 30 June 2025. Accessed 28 Nov 2026.
- Investment and Special Economic Zones Act, No. 6 of 2025. TanzLII, 2025. Accessed 28 Nov 2026.
- The legal framework governing PPPs in Tanzania and PPP pipelines. TISEZA, July 2025. Accessed 28 Nov 2026.
- Overview of PPP. Zanzibar PPP Department, page current 2026. Accessed 28 Nov 2026.
Figures to confirm before you act
- The final project count, 16 or 17, and whether Bumbuli or Kilindi quarries remain on the list.
- Which project is the yellowfield one, and which are brownfield.
- The unsolicited review fee under regulation 9(1) as amended by GN 838A of 2023, reported as 0.1% of capital cost capped at USD 50,000; confirm with the PPP Centre.
- The land mechanism each council will use for a foreign-controlled SPV; confirm with TISEZA and the Ministry of Lands.
- The tourism licence fee for a hotel operator in Tanga; confirm with the licensing authority.
- Whether section 28 of Cap. 103 now points to the 2025 investment Act; confirm with TISEZA.
This article is general information based on official sources available at the date of publication. It is not legal, tax or financial advice. Laws and notices change. Verify with the issuing authority or consult Zatra before acting.
Frequently asked questions
Can I apply for a Tanga project today?
No tender or expression of interest has been published for the 17 projects. You can approach the council that owns a site and register with the PPP Centre. An investor-led prefeasibility study can also be lodged with the council as an unsolicited proposal.
Who owns the Tanga project sites?
The councils of Tanga Region. Each of the 17 shortlisted projects holds a title deed, which is why it passed screening. The council acts as contracting authority and its accounting officer signs any agreement after the required approvals and vetting.
Does the government put money into these projects?
It can. The PPP Centre said the government may co-finance capital costs through viability gap funding. That support suits solicited projects. An unsolicited project that seeks exemption from competitive bidding must show it needs no guarantee or financial support.
Can a Tanzanian SME bid on the smaller sites?
Yes. Nothing in Cap. 103 limits PPPs to large or foreign sponsors. Bus stands, a business centre of 1,069 square metres and the Pangani fish market suit local operators. Councils are also asked to create citizen empowerment opportunities.
How long does a council PPP take to sign?
No timetable has been published for Tanga. The steps run from prefeasibility to feasibility, procurement, negotiation and Attorney General vetting. Small-scale projects skip Steering Committee recommendation, but the study and review stages still take months.
Can the council hold shares in my project company?
Yes. Section 25(2) of Cap. 103 lets a public entity hold up to 25 percent of the equity in the special purpose vehicle. The regulations add that it must show adequate financial capability to take that stake.
What happens if a dispute arises with the council?
Section 29 requires the parties to try negotiation first. If that fails, they may agree arbitration under Tanzanian arbitration law, ICSID rules or an applicable investment treaty. The agreement is governed by Mainland law, so involve an advocate early.
Is there a similar pipeline in Zanzibar?
Zanzibar runs its own projects under the PPP Act, No. 8 of 2015, through the PPP Department in the President's Office. Mainland approvals and TISEZA certificates do not reach the islands, where ZIPA handles investor registration.
Sources & regulators
Verify before filing: Rates, forms and thresholds move by Finance Act, Government Notice and portal revision. Confirm the live schedule on the mandate-holder portal before you budget or submit. Law-firm alerts and Big Four notes are discovery only.
- 17 PPP projects open in Tanga to investors: TanzaniaInvest, 13 November 2026; project list, areas and forum speakers. Accessed 2026-11-28.
- Tanga turns to private investors (forum preview): The Respondent Online, 11 November 2026; forum preview by Dr Bravious Kahyoza. Accessed 2026-11-28.
- Tanga opens 17 PPP projects to investors, studies pending: Streamline Feed, 13 November 2026; feasibility studies still to be prepared. Accessed 2026-11-28.
- Can private capital deliver Tanga's promised economic transformation?: The Respondent Online, 26 November 2026; no agreement signed, quarterly progress reports. Accessed 2026-11-28.
- Public Private Partnership Act, Cap. 103 R.E. 2023: PPP Centre and Office of the Attorney General, R.E. 2023 (2025 print); ss.2, 3, 10, 13, 18, 20, 21, 22, 24, 25, 28, 29, 33 read. Accessed 2026-11-28.
- Public Private Partnership Regulations, 2020, GN 37 of 2020: Ministry of Finance, published 24 January 2020; regs 3(4), 7, 9, 10(3), 16(2) read. Accessed 2026-11-28.
- Public Private Partnership Centre: PPP Centre, home and news pages current November 2026. Accessed 2026-11-28.
- Public Private Partnership Act amended: FB Attorneys, 24 July 2023; Act No. 4 of 2023 passed 13 June, gazetted 14 July 2023. Accessed 2026-11-28.
- Tanzania PPP Regulations amendments, 2023: Clyde and Co, 10 June 2024; GN 838A of 2023 summary. Accessed 2026-11-28.
- Land Act, Cap. 113: TanzLII, text as at 30 June 2025; s.19(2) read. Accessed 2026-11-28.
- Investment and Special Economic Zones Act, No. 6 of 2025: TanzLII, Act No. 6 of 2025. Accessed 2026-11-28.
- The legal framework governing PPPs in Tanzania and PPP pipelines: TISEZA, July 2025; framework and 83-project national pipeline. Accessed 2026-11-28.
- Overview of PPP (Zanzibar): Zanzibar PPP Department, page current 2026; PPP Act No. 8 of 2015. Accessed 2026-11-28.
Disclaimer
This article is informational orientation. It is not legal, tax or investment advice and not a government decision. Tanzanian instruments move by Act, Government Notice, Finance Act and portal revision. If a sentence here disagrees with the live mandate-holder, the mandate-holder wins. Zatra Consultants Limited does not issue licences, permits, tax clearances or approvals, and gives no assurance of any regulatory or banking outcome. Professional fees are published only on /pricing/.